Project Milestones
Project Milestones
1. Mobile Avian Laboratoro (MAL) assembly starts, 01/10/2013
2. Project Field Teams Established, 31/10/2013
3. Operational Planning Started, 01/11/2013
4. Reconnaisance Field Surveys Started, 01/11/2013
5. Project Steering Committee Established, 30/11/2013
6. Project Advisory Committee Established, 31/12/2013
7. 1st Project Workshop Implementation, 31/01/2014
8. Project WebSite Operational, 02/03/2014
9. Awareness Campaign Started, 01/06/2014
10. Field Personnel Trained by External Experts, 01/06/2014
11. Communication Monitoring Started, 30/06/2014
12. Preparation of Information Material Started, 01/10/2014
13. Post-construction Assessment Started, 1/01/2015
14. Training Seminars Started, 01/01/2016
15. International Symposium Implemented, 30/04/2017
16. Production of Good Practice Guide (PPG) and Decision Support Tool (DST), 30/04/2017